Only three months ago, the immense construction site at Indiana's Marble Hill nuclear power station alongside the Ohio River bustled with 8,000 workers. Now the cranes and earth movers at the plant stand idle, and a shroud of snow covers the project's jagged skeleton. Last week Public Service Co. of Indiana, Marble Hill's principal builder, announced that it would abandon the half-finished plant altogether. Marble Hill has already eaten up some $2.5 billion, making it the most expensive nuclear power project ever to be dropped. The decision brings the total number of cancellations of U.S. nuclear plants since 1974...